Compare two solar forecasts on the same measurement and weather basis. A worked example separates installed capacity from specific yield.

Two installers have visited the same property, yet their solar production forecasts differ. Before you treat the gap as a sign of quality, reconstruct what each forecast measures. One design may use every available roof face while the other leaves more space around a roof window. A forecast may report the electricity produced after conversion, while a financial summary from another bid may show only the surplus available for sale. The figures become comparable once their boundaries, units and underlying assumptions identify what each quantity actually represents.
This guide works through a numerical example and puts the two offers on a common basis. By the end, you will have a reconciliation sheet to send separately to each installation company. It helps you ask for a revised version, understand the remaining gap and identify points to verify at the building. Start from the original forecasts and keep the results of any alternatives. This paper trail supports a decision weeks later, even if another person takes responsibility for the quote in the meantime.
Define the quantity you are comparing
Write the full name of the quantity beside the number. For a technical comparison you might choose annual alternating-current energy at the inverter output, before any allocation to direct consumption, battery charging or grid export. Ask whether power limits, planned stoppages or inverter clipping are already included in that figure. Other studies may describe energy on the module side, generation registered by a meter or a financial measure such as expected compensated exports.
Then check the period. A representative weather year, a multi-year average and a shortened first year of operation answer different questions. Use a complete year for a technical design comparison. If commissioning is planned for autumn, prepare a separate cash-flow scenario for the shorter opening period. Keeping those two questions separate avoids interpreting a calendar effect as a genuine difference in annual performance, especially when quotes issued weeks apart use different completion dates.
Compare output per unit of installed capacity
In a hypothetical example, offer A forecasts 9600 kWh per year from 10 kWp, or 960 kWh per kWp. Offer B forecasts 8400 kWh from 8 kWp, or 1050 kWh per kWp. In annual energy, A is ahead by 1200 kWh. Per unit of installed capacity, B gives a higher estimated yield. These figures can both be correct once you have confirmed that their measurement boundaries match.
Show both calculations and keep the original numerator and denominator visible. A larger project may use an additional roof face or include more modules near a parapet. The specific yield can therefore fall while total production rises. Those figures tell you something about two distinct decisions: how much available space to cover and how effectively the proposed layout uses its capacity. Keep both indicators on the same sheet and use their labels consistently when discussing the proposals.
Separate the effects of array size and layout
Ask for both drawings with module counts and the orientation and tilt of each group. Put them side by side and circle roof areas included in only one variant, particularly near chimneys, skylights, trees and disputed setbacks. Check the materials list against the drawings when the installer offers multiple commercial variants. A table from one design can easily be attached to a roof plan from another, especially after a revision made during a site visit. A marked-up drawing with deliberate revisions lets you identify a removed skylight clearance, an altered ridge offset or a different array boundary without having to infer geometry from the total power rating.
A practical test calculates offer A with the reduced geometry used by B. In a later step, keep the same layout and change only the installed capacity to separate the module count from the specific yield. Record which factors can genuinely be aligned and which reflect a feature of the proposed installation. A roof section that only one company has reliably committed to using remains a real difference worth keeping in your comparison.
Choose a common weather reference
A single array layout can produce different forecasts when the models use different irradiation data or historical periods. Ask for the full name of the dataset, observation window and software version. The Joint Research Centre manual for PVGIS distinguishes average yield from the variability between years, which is calculated from the years covered by the selected solar radiation database.
A common tool gives you a separate reference point. Keep files or screenshots for the two trials, using the same position and irradiation source and documenting the terrain parameters. Change one variable at a time. If you switch both the installer’s design and the weather model in a single run, you cannot identify which choice explains the shift. Record each observed effect on the comparison sheet and keep any export file in the same project folder.
Put shading on its own line
Separate the distant horizon from obstacles near the building. A geographic model can represent hills or mountains within its resolution. A chimney, neighbouring extension or nearby tree often requires direct observations of the property. A clear day can help you identify obstacles, while the path of the sun changes over the year. Dimensioned plans, a site visit or a dedicated shading assessment can complete the terrain-based calculation when the details matter.
Ask each installer how the forecast treats persistent shade and seasonal effects. Note whether the shadow affects a module calculation, changes the layout or is already included in an overall system loss. Clear labelling helps you avoid applying the same correction twice. It can also explain why a short strip beside a roof window is significant to the forecast, even if the shaded region looks small in an aerial image or on the outline drawing.
Check which losses the forecast already includes
The Joint Research Centre’s PVGIS manual describes production estimates incorporating system losses. Depending on the software and the installer’s method, temperature effects, conversion, cable losses and downtime may appear in different fields. Ask which corrections are already modelled before a broad loss factor is added. That sequence determines whether two apparently similar percentages are actually comparable.
Record where each deduction takes effect. A reduction in available irradiance and a loss applied at the inverter output describe different points in the calculation. If a power restriction applies, ask when the limit affects production and what the total annual impact is. Note whether the assumption comes from software defaults, equipment specifications, a site measurement or a network condition. This helps you direct the next question to the person who can substantiate it.
Compare monthly output and the shape of the curves
The annual figure conceals when the difference appears. Ask both companies for monthly values. If the gaps are concentrated in cold months, check the treatment of the horizon, snow, tilt and model resolution. If they appear mostly around midday in summer, check the conversion capacity, the grouping of modules and the treatment of possible peaks that exceed inverter capacity. A month-by-month comparison gives you a better place to start asking questions.
With a heat pump, a shared building or a controllable charger, ask for an hourly export in the same format if both installers can supply it. Request the estimated output of the installation and, in a separate table, its modelled allocation to different uses. For the eventual choice, discuss when the extra electricity coincides with genuine flexible demand and which households or equipment can use that production without assuming changes in behaviour that no one has agreed to.
Ask for a sensitivity test you can repeat
Keep the base design, then consider documented alternatives such as removing modules near a shadow, changing an assumption about summer ventilation or imposing a measurable export limit at the connection point. Use the same weather series and measurement boundary for every trial. List the original file and the input that causes the change. This leaves a reproducible trail even when the forecast was produced in a proprietary application that the property owner cannot operate directly.
An informative range explains the type of uncertainty. A cloudier year is a difference in weather. A changed layout reflects a design choice. Poorly measured shade is a site detail for further inspection. To prepare a conservative financial scenario, choose which assumptions can reasonably be less favourable and describe the mechanism. This improves the commercial decision and retains the distinction between an estimate used for planning and any separate commitments written into a contract.
Reconcile the replies before you sign
Send the same table to both installers. Ask them to confirm the measurement boundary, layout, weather period, local shading, included losses, any power limits and the monthly profile. If they issue a new forecast, record its revision and date. A reply that documents the basis of the forecast gives you something to refer to even when several slightly different reports remain in the same email thread.
If additional roof area accounts for the differences, discuss its expected cost and how the energy might be used. If the gap remains substantial with the same layout, ask which factor still explains it and how the provider will check that factor. Save the chosen file to compare future measured generation on an equivalent basis. Generation, allocation among uses and the finances become separate, traceable comparisons, each suited to a particular decision.
Make a comparison sheet the installers can annotate
Set out one row per input or calculation step, with separate columns for each offer, its source and the remaining question. Include the final layout, capacity, units, measurement point, climate reference, treatment of obstacles and the calculation of system losses. Keep assumptions visible. A cell clearly labelled as open makes it harder to mistake an unsupported entry for a condition that the installer has already checked.
As you receive replies, add the relevant document reference next to each correction. A dimensioned roof plan, an inverter specification and a generation export perform different roles. Versions can coexist in a single email thread, especially after the roof has been inspected in greater detail. The worksheet should indicate which layout corresponds to the current price and which results are informative scenarios that are available for comparison but are outside the latest offer.
Give the input quality more weight than the decimals
A detailed simulation can show decimal places that are finer than the records of the building justify. Judge the quality of the input data before looking at the length of the printed result. A gap consistently attributable to a carefully measured roof plane is decision-relevant. A narrow gap after a rough model has been adjusted is a good reason to understand the uncertainty before putting the two companies in a ranking.
Ask which differences the installer can check during a visit. Examples include usable space around skylights, the expected growth of vegetation, cable routes, inverter location and operating conditions. Request a dated answer distinguishing measurements from values taken from a database. This lets the team focus its visit on details likely to change the design or materially affect the commercial estimate, while recording the other factors under the appropriate assumptions.
Send each question to the right person
The system designer or installation company should explain its yield calculation. A grid operator can account for its connection conditions and restrictions at the metering point. Future building use and consumption can be discussed with owners, management and the people who will actually occupy the space. Directing each question to the appropriate person improves the chances of a useful answer and limits the number of contradictory versions of a single proposal.
To close the comparison, write a short decision note covering the strengths of each layout, the source of the numerical gap and any points to confirm before ordering. Record who can answer each question and which document you expect. Attach the dated reports to the selected contract. After commissioning, this record helps you choose an appropriate comparison period when the first year is incomplete or the building’s consumption needs have changed.
Choose a level of detail suitable for your building
An open, symmetrical roof can often be compared using a few well-documented inputs. When a property has several faces, older extensions or unusual electrical arrangements, an average may conceal the group responsible for most of the difference. Ask whether the report can show output by roof face or by module group. Give each line a corresponding reference on the drawing and reconcile the individual amounts with the forecast for the installation as a whole.
Check whether a claim about equipment performance has actually been reflected in the forecast for your building. A manufacturer may document a particular capability without an installer having calculated its effect on your roof. Connect the feature to the local conditions and to the choice it could influence. A clear record keeps the offers understandable for your actual project even if more alternatives arrive or an earlier version of a forecast is circulated again.